Kreisstraße AS 30 between Aschach and Amberg-Nord: reopening after 5 months
Kreisstraße AS 30 between Aschach and Amberg-Nord: reopening after 5 months
Retening of the district road AS 30: An important step for traffic safety
traffic flow improves enormously
The district road AS 30 between Aschach and Amberg-Nord will be released for traffic again from August 7th. After less than five months of construction, drivers, commuters and heavy goods traffic can use the newly designed road. This early completion of the construction work is an important milestone for the traffic structure in the region.
investments in the future
The redesign of the district road required an investment of around 3.7 million euros, of which around 1.15 million euros come from the district's own contribution. These financial resources flowed into measures that not only expanded the road width from 6 to 8 meters, but also created a roundabout at the confluence with the state road Amberg-Hirschau. These large investments not only contribute to the relief of traffic, but are also a sign of the commitment to improve the infrastructure.
important role for industry
District Administrator Richard Reisinger emphasizes the importance of AS 30 because it represents a central transport connection to the adjacent industrial area. The road plays a key role in transport and logistics, which strengthens companies in the region. Reisinger emphasizes that faster completion contributes to not only maintaining the business in Amberg-Nord, but also expanding.
increasing competitiveness of the region
The new confluence according to Aschach acts as a security measure and has defused an earlier focus of the accident. Matthias Kolb, head of the civil engineering office, emphasizes that despite initial difficulties, such as weather problems and demanding building basic conditions, the construction measure was quickly promoted. The rapid building therefore not only stands for efficiency, but also contributes to the long -term improvement of traffic safety in the region.
thanks to the participant
In a thank you to the employees involved, the building contractors and the residents, District Administrator Reisinger expresses his appreciation for their patience during the construction period. This cooperation underlines the sense of community and the use of everyone involved in order to improve the infrastructure for all road users.
The reopening of the Kreisstraße AS 30 is therefore not only a short-term relief for traffic, but also an important step towards a future-proof and safe transport connection in the Amberg-Sulzbach region.