A565 expansion in Bonn: Tausendfüßler receives urgently needed renewal

<p> <strong> A565 expansion in Bonn: Tausendfüßler receives urgently needed renewal </strong> </p>

FAQ to the A565 in Bonn: Tausendfüßler is six lane

The A565 in Bonn is significantly expanded as part of the 2030 Federal Transport Infrastructure Plan. An essential part of this project is the bridge train, which is known locally as a "thousand foot", and extends between Bonn-Endich and the Bonn-Nord motorway junction. This expansion is based on infrastructure needs and the rising traffic volume on this important traffic route.

What is the "thousand feet"?

The thousand football comprises two main constructions: the Brücke Dransdorfer Weg and the actual millipede. As a clamping concrete construction that was built in 1959, it must now meet the requirements of modern traffic. The expansion, which is to be completed by the end of 2026, includes an extension to six lanes and setting up a hard shoulder to increase the safety of road users.

Details for the expansion

The planned work stipulate that the two -track bridge Dransdorfer Weg, the three municipal roads and several tracks of Deutsche Bahn are covered, and the thousand football with a total length of 630 meters are now extensively renewed. During the expansion, care is taken to ensure that the traffic remains as far as possible. In order to minimize the load during the construction period, special truck restrictions are provided for the bridge sections.

costs and time frame

The costs for the necessary expansion amount to around 293 million euros, a sum that is currently being calculated due to changes in the construction price. The entire construction period is estimated at the age of six, whereby the planning phase is still underway. The start of construction is aimed at the end of 2026, and it is expected that separate traffic tours will be made possible during this time in order to keep traffic and reduction of the traffic flow as low as possible.

environmental and noise protection

As part of the project, comprehensive environmental protection measures are planned. The legally required filtering of rainwater is carried out by special treatment plants that are created to minimize the environmental pollution. In addition, noise protection walls are intended to make residents easier.

In summary, it can be seen that the planned expansion of the A565 in Bonn represents a necessary measure in order to take into account the increasing traffic load and increase traffic safety. With a clear focus on environmental protection and the minimization of stress for residents, the project brings with it both challenges and opportunities.