In Balingen, there are significant lane renewal work, which should ensure both traffic safety and the maintenance of the streets. The district office of the Zollernalb district has announced that the work on the connection branches of the B 463 to L 446, near the Gehrn industrial area, will begin. These measures are not only necessary, but also urgently to meet the increasing transport requirements, such as The district office reports .

The renewal work includes the complete exchange of the bituminous road structure on both connection branches to the L 446. In addition, the lane ceiling on the delay traces is renewed from the B 463 to the connection branches. These extensive work are planned in such a way that they are not carried out at the same time in order to maintain the flow of traffic as much as possible.

Template of the construction work

The first phase of the work begins on Monday, November 18, 2024, in the direction of Albstadt and should last until December 6, 2024, provided the weather conditions are favorable. The work for the connection system towards Balingen is scheduled for the coming spring and should be completed by April 2025. During the construction period, the connection was completely blocked from the B 463 to the L 446, which will bring considerable restrictions for road users and residents. The two -lane lane of the B 463 is narrowed into a lane in the construction site area, which also complicates the Situation.

traffic forecasts and costs

The total measure has a length of around 2.50 km and is estimated at around 26 million euros. The traffic forecasts for 2030 show that the strain on this route will increase significantly, with an expected number of 33,000 motor vehicles per day. This illustrates the urgency of the renewal work in order to meet the future requirements, such as from the responsible authority reports .

The district office asks all road users for understanding the inconvenience that can arise during the construction period. These measures are crucial to increase security on the streets and to improve the infrastructure for the future. The renewal of the road will not only extend the lifespan of the streets, but also increase security for all road users.