Glass fiber expansion in Neumünster: Confirmation delay faster internet!

Glass fiber expansion in Neumünster: Confirmation delay faster internet!
Neumünster, Deutschland - Currently, the fiber optic expansion in Neumünster faces a number of challenges that affect the project. Stadtwerke Neumünster (SWN) had planned to start laying the fiber optic lines in the city center at the beginning of the year. However, there were delays, which are primarily due to annual discussions and negotiations with Deutsche Telekom. Hundreds of new customers in the Böckler settlement and in the middle of the city have already been informed about these delays, while SWN cannot currently specify binding completion dates, such as KN-Online reported.
The plan stipulates that by the end of 2025 the western part of the city center, from Wippendorfstrasse to Sedanstrasse, will be connected to the fast internet. At the beginning of the year, purple cables were already laid in the streets under the sidewalks. Some assembly work in the houses is preferred, although the cable is not yet up to the door. A SWN team has also found a compromise to relocate the lines in the city center together with Telekom to avoid double road openings.
coordination of the construction sites
Mayor Tobias Bergmann (SPD) initiated intensive discussions between the municipal utilities and Telekom. The aim is to optimize the coordination of the civil engineering work: in some areas, Telekom will dig and at the same time lay the SWN lines, while in other areas SWN takes over the excavations. This coordination is necessary to prevent one construction site from following the next, which could have negative effects on retail and residents. The CDU parliamentary group examines the possibility of introducing a municipal statutes to regulate construction sites, which this time is inspired by an existing set of rules in Hamburg, reports Shz .A spokeswoman for the Stadtwerke, Saskia Ullrich, emphasizes that one wants to minimize the impairments for the citizens. The planning spokeswoman for the CDU, Franka Dannheiser, refers to the specialist statement from Hamburg, which could regulate excavations in a rhythm of three to five years. In this context, a new draft agreement was submitted by Telekom, which is now being examined.
project restart and digitization
in parallel to this expansion process, a new project for fiber optic expansion in Neumünster has started. In cooperation with GIGA5, this pilot project aims to equip around 400 residential units with modern fiber optic infrastructure. If the end is successful, up to 6,000 additional residential units in the region could follow. The site manager Andreas Ciesynski has taken responsibility for the implementation of the project, which is intended to promote the digitization and modernization of the city. Netzkontor emphasizes the importance of this cooperation for the digital future of Neumünster.
Overall, the progress of the fiber optic expansion in Neumünster is still being observed closely. Up to 14,200 households could be connected to the new fiber optic network, with 12,000 active customers currently existing in Neumünster. Another 3,000 customers are waiting for the connection in processing. The coming months will be crucial to enable the connection to modern Internet in a timely manner.