District roads in the Harburg district: 285,000 euros for important renovation!

Transparenz: Redaktionell erstellt und geprüft.
Veröffentlicht am

The Harburg district will be renovating district roads for 285,000 euros from July 7th. Work will last until mid-August, road users be careful!

Landkreis Harburg saniert ab 7. Juli Kreisstraßen für 285.000 Euro. Arbeiten dauern bis Mitte August, Verkehrsteilnehmer aufgepasst!
The Harburg district will be renovating district roads for 285,000 euros from July 7th. Work will last until mid-August, road users be careful!

District roads in the Harburg district: 285,000 euros for important renovation!

A lot is happening in the Harburg district, as a comprehensive renovation of the district roads starts on Monday, July 7th. This measure, which is scheduled to last until mid-August, is being carried out by residents and road users with a budget of 285,000 euros. In total, an impressive 78,000 square meters of road surfaces are on the agenda that need to be repaired. Loud Seevetal current The project aims to close network cracks and repair porous surfaces.

In order to carry out this maintenance work efficiently, a special machine is used that carries out the repairs in three steps. First, a bituminous binder is applied, followed by the distribution of grit on the surface. The final step is rolling in the grit to ensure a stable road surface. However, road users must be prepared for restrictions as speed limits of 30 to 40 km/h apply at the construction sites.

Construction site information and diversions

Full closures will be necessary in the first week of construction work. District road 52 from Sieversen to Bachheide will be closed for two days between July 16th and 20th. District road 55 between Hanstedt and Dierkshausen will also be closed for one day during the same period. Detours are signposted in good time so that road users are not left high and dry.

Like the website of Harburg district explained, current traffic disruptions can be viewed using the construction site atlas. The locations of construction sites, line excavations and also events that could influence traffic are displayed there. The information is available up to 14 days before construction begins and offers citizens the opportunity to stay informed at all times.

In addition, daily construction sites can be received directly on your cell phone via BIWAPP, which is particularly practical for anyone who is on the go regularly. This way you can always stay up to date without constantly checking the construction site atlas.

Foresight of future measures

The measures in the Harburg district are part of a larger project that is intended to sustainably improve the transport infrastructure in the region. The aim is to ensure not only the road itself, but also the safety of road users in the long term. What is important is good cooperation between the transport authorities and the companies active in the region. This coordinated approach is also carried out by the Streets.NRW offered, which defines different types of construction sites and participates in the planning.

For everyone who is driving through the Harburg district in the coming weeks, it is important to keep your eyes open and pay careful attention to the detours. A renovated road not only offers more comfort, but also a safer driving experience. Driving in the Harburg district becomes a lot more pleasant!