Construction of the Windstrom project A-Nord starts: Earth cable between Kleve and Meerbusch!
Construction of the Windstrom project A-Nord starts: Earth cable between Kleve and Meerbusch!
Kleve, Deutschland - The construction work for the important wind power project A-Nord picks up speed! Work on the ground cable connection between Kleve and Meerbusch will begin next week. The Federal Network Agency approved the project, as the transmission system operator Amprion announced on Thursday. Matthias Gierlich, overall project manager of the A-Nord, was enthusiastic: "We are very pleased that after intensive preparation, the construction of the approximately 58-kilometer section NRW3A is being started."
Planning for this ambitious project has taken around eight years. With the start of the construction work, an important step towards sustainable energy supply in the region is taken. More details can be found in a detailed report on rp-online.de.
Details | |
---|---|
Ort | Kleve, Deutschland |