Traffic closure in Sigmaringen: This is how the diversions run

Traffic closure in Sigmaringen: This is how the diversions run

permanent blocking of the main passage in Sigmaringen: Effects on the residents and the local economy

The upcoming blocking of the B32 and Mühlbergstraße in Sigmaringen for security work on a railway bridge will present the residents and the local economy with challenges. The work that continues from Tuesday, July 9th to Wednesday, September 4, will significantly affect traffic, which requires diversions.

difficult times for road users

The diversions are carried out in four construction phases, with the first section on Tuesday, July 9th, starting and until Tuesday, July 16. During this time, traffic from Sigmaringendorf will be diverted via Binger Straße and Hohenzollernstraße. Pedestrians and cyclists have to dodge on the sidewalks and exercise special caution.

The second construction phase follows from July 17th to 19th with a full closure of the railway bridge. It is recommended to observe the signposted diversions in order to avoid traffic jams and not to endanger the construction work.

outlook for the future

Mühlbergstraße is expected to be released again for traffic from September 4, which will be a relief for all those affected. The city of Sigmaringen asks for understanding for the inconvenience during this time and thanks the residents and road users for their patience.

It is important to stick to the signposted diversions during this block and to take into account pedestrians and cyclists. Together we can master this challenge and emerge from it.