Replacement bridge comes: Huntbrücke in Elsfleth is repaired as soon as possible
Replacement bridge comes: Huntbrücke in Elsfleth is repaired as soon as possible
Preparations for repairing the Huntbrücke After the ship's accident on July 23, 2024, gives rise to speed. A significant step will be taken in the coming week: the delivery of the load -bearing part of the replacement bridge. This development is not only important for the railway company, but also has far -reaching effects on the local economy and the population of the Wesermarsch region.
delivery of the replacement bridge in sight
The railway has announced that the first part of the replacement bridge will arrive in Elsfleth early next week. At the moment, the workers are busy securing the hanging steel carriers and reducing the tracks and the overhead line in order to clear the way for the repair. Such work is necessary to ensure the safety of the new bridge.
background of the accident
The ship's accident, in which an inland ship hit the railway bridge, led to considerable damage, both on the bridge structure and on the ship involved. The incident in which the tanker bridge house was almost completely torn down not only stopped train traffic, but also severely affected the connection of the ports along the Weser. This could have nationwide economic consequences for the region, since the port industry is dependent on a stable transport connection.
economic effects on the region
The current blocking already results in significant consequences for commuters and especially for the companies in the adjacent port systems. Lower Saxony’s Minister of Economics Olaf Lies emphasized that the repair of the bridge is imperative to keep the loads on the local economy as low as possible. Every week in which the repair can be promoted, is considered a step in the right direction.
technical challenges
Nevertheless, not all spare parts are available yet. In particular, the specially made bridge bearings have been missing so far, which means that the exact time frame for the full repair of the bridge is still uncertain. However, the railway has made it clear that the new part of the bridge can be successfully lifted with a floating crane, but it will take about a week and a half to restore the tracks, the overhead line and safety technology.
outlook for the coming weeks
The Huntbrücke is already a central topic for the local community. The foundation for future stability is placed, with the preparations for restoring train traffic special attention. The interaction between the authorities, the train and the local population will be crucial to restore the flow of traffic as quickly as possible.
In summary, it can be said that the timely repair of the Huntbrücke is not only crucial for the railway itself, but also remains of great importance for the entire economy in the Wesermarsch region.- Nag